Project Description
Detailed integrity survey for all pressurization systems in gas field for all offshore and onshore platforms. The project
included the following:
- Carry out detailed engineering studies to show means of rewarding and upgrading these defects.
- Preparation of detailed specifications and material take-off lists to show all needed materials for each platform.
- Carry out detailed casting survey to estimate the budget needed to finalize the work.
-
Preparation of detailed time schedule for each platform showing the needed duration to repair/replace all defected
items.
- Establish a detailed execution strategy using the state-of-the-art technologies to minimize the shut-off duration.